Passive fire protection applied to structural steel beams in a commercial building
Passive Fire Protection for Structural Steel

Structural Steel Fire Protection Systems

Protection thickness is member-specific — not a project-wide figure

The required thickness for each steel member is calculated from the approved system assessment using the actual section factor and critical steel temperature. A single thickness applied across a project will be inadequate for slender members and excessive on compact ones.

This page compares the principal passive-fire protection routes for structural steel. Detailed intumescent coating specification — including section-specific loading, primer, topcoat, DFT and repair requirements — is covered on the dedicated Intumescent Coatings page.

This page compares the principal passive-fire protection routes for structural steel. Detailed intumescent coating specification — including section-specific loading, primer, topcoat, DFT and repair requirements — is covered on the dedicated Intumescent Coatings page. Forti Nova must not calculate or guess the structural fire-design inputs. They must be supplied or confirmed by the competent project design team.

The Requirement

Steel is non-combustible but thermally conductive. Its mechanical strength reduces significantly as temperature increases. Without passive fire protection, an unprotected structural steel member can lose sufficient load-bearing capacity to cause collapse within minutes of fire exposure.

Building Regulations Approved Document B, BS 9999, BS 9991 and the structural fire design standards require structural elements to maintain their load-bearing function for a defined fire-resistance period — established from the building use, height, floor area and occupancy. The required period for each element must be confirmed from the fire strategy by the fire engineer or Building Control.

The fire-resistance period, critical steel temperature and section factor for each member must be confirmed by the structural or fire engineer before any protection system or thickness is specified. These inputs are not universal and cannot be assumed from building type or member description alone.

Before Any System is Proposed
  • Fire strategy confirmed by fire engineer or Building Control
  • Required resistance period established for each structural element
  • Section factors calculated for actual members and exposure conditions
  • Critical steel temperatures confirmed from structural fire design
  • No protection system can be specified without those inputs
  • No thickness value is valid without the approved product assessment
Design Inputs Required Before Selection

What the Structural Fire Design Must Confirm

The protection system, required thickness and qualifying evidence cannot be selected until these inputs are established for each member by the competent project design team. Forti Nova must not calculate or guess the structural fire-design inputs.

Fire-Resistance Period

Source: Fire engineer / Approved Document B / BS 9999 / BS 9991

Defines the required duration — different elements may require different periods. Determined by building use, height, floor area and occupancy.

Cannot be assumed from building type. Each structural element must be confirmed against the fire strategy.

Critical Steel Temperature

Source: Structural fire design (EN 1993-1-2)

The temperature at which the member loses load-bearing capacity under its design fire load. Depends on structural utilisation or load ratio — not universally 550°C.

A more heavily loaded member has a lower critical temperature and may require greater protection. Must come from the structural fire design for each member.

Section Factor (Hp/A)

Source: Calculated from section geometry and exposure condition

Ratio of heated perimeter to cross-sectional area (m⁻¹). Higher section factors heat faster. Changes with beam vs column, open vs hollow section, three vs four sides exposed.

Must be calculated for each actual member and exposure. Cannot be estimated from catalogue tables without confirming exposure.

Member Type and Geometry

Source: Structural drawings

Universal beams, columns, hollow sections (CHS, RHS), castellated beams, connections and built-up members each behave differently in fire. Assessment coverage must be confirmed per member type.

Not all protection systems are assessed for all member types. Coverage must be confirmed from system assessment documentation.

Environmental Exposure

Source: Project information / BS EN ISO 12944

Internal dry, internal humid, external and chemically exposed environments each place different demands on the protection system, primer and topcoat. Internal-grade systems must not be applied externally.

The assessment category must cover the actual exposure. Not all systems have external-grade assessment.

New-Build or Existing Construction

Source: Project information and existing building records

Existing buildings require identification of existing protection, original member schedule, changes to occupancy, fire strategy and structural alterations before any protection specification proceeds.

Visual appearance alone cannot establish the remaining fire performance of an existing system. Original documentation must be located or alternative assessment arranged.

Access and Finish Requirements

Source: Project programme and architectural specification

Application, inspection and maintenance access determine which protection routes are practical. Finish requirements — exposed steel, concealed or rough-textured — may eliminate certain routes regardless of fire performance.

Access constraints for DFT measurement, board installation or spray containment must be confirmed before committing to a system.

Protection Routes

Comparing the Four Protection Routes

No single route is universally appropriate. Selection depends on the structural fire design inputs, environmental exposure, appearance requirements, access, programme and whole-life factors. All routes require project-specific assessment against the confirmed structural fire design.

Reaction to fire ≠ Structural fire resistance. Products classified under EN 13501-1 are surface lining performance classifications. They do not provide structural fire resistance for steel members and must not be substituted for a tested structural protection system. See Fire Protection Coatings for the surface-coating route.

Intumescent Coatings

Reactive coating — thin-film or thick-film

Appearance

Paint-like, slim profile — suitable for exposed architectural steel

Fire-Resistance Periods

Available fire-resistance periods depend on the specific tested or assessed system, member configuration, design inputs and installed build-up.

Thickness Control

Member-specific DFT from product loading schedule — varies per member

Inspection Method

DFT measurement per member using calibrated gauges

Added Weight

Minimal added weight

Access Requirement

Requires access during and after application for DFT measurement

Programme Impact

Cure time between primer, intumescent and topcoat coats

Repairability

Local repair if system is identified and compatible material confirmed

Environments

Internal and external grades — confirm from assessment documentation

Strengths

  • Slim profile — minimal section-size increase
  • Suitable for exposed architectural steel
  • Member schedule approach supports member-level QA
  • Assessments available for a wide range of commercial section types

Limitations

  • Accurate DFT measurement required on each member — critical for QA
  • Primer and topcoat compatibility must be confirmed from system documentation
  • Environmental exposure category must be within assessment scope
  • Not visually inspectable for fire performance after application
Intumescent Coatings — Full Specification Detail

Fire-Protection Boards

Fixed board or proprietary casing

Appearance

Boxed profile around member — profile increase dependent on build-up

Fire-Resistance Periods

Available fire-resistance periods depend on the specific tested or assessed system, member configuration, design inputs and installed build-up.

Thickness Control

Fixed build-up from system assessment; board thickness and layers confirmed at installation

Inspection Method

Visual — dislodgement, damage, moisture, fixings, joints, junctions

Added Weight

Board plus framing adds weight and section bulk

Access Requirement

Installation requires clear perimeter access; concealed connections must be detailed before enclosure

Programme Impact

Defined by installation sequence; no cure time required for the board itself

Repairability

Local board replacement if board type and fixing schedule are known

Environments

Dry internal as standard; moisture-resistant and external grades — confirm from assessment

Strengths

  • Robust — impact- and moisture-resistant grades available
  • Defined installation tolerances support consistent QA
  • Visually inspectable for completeness and condition
  • Suitable for connections and irregular profiles where coating access is limited

Limitations

  • Greater section-size increase than thin-film intumescent
  • Connection, junction and penetration detailing can be complex
  • Not appropriate where slim profile or paint-like appearance is required
  • Fixing penetrations must be within the confirmed assessed build-up
Request Board or Encasement Assessment

Tested Spray-Applied Protection

Applied passive-fire material — composition confirmed from system documentation

Appearance

Rough-textured surface — not suitable for exposed architectural finishes

Fire-Resistance Periods

Available fire-resistance periods depend on the specific tested or assessed system, member configuration, design inputs and installed build-up.

Thickness Control

Applied thickness from system assessment — measured before concealment; cannot be measured after enclosure

Inspection Method

Thickness measurement before concealment is essential; visual inspection thereafter

Added Weight

Material added weight — confirm structural loading where relevant

Access Requirement

Containment and dust management required during application

Programme Impact

Rapid area application; moisture-sensitive during curing period

Repairability

Repair possible if original system is identified and compatible material confirmed

Environments

Primarily internal; external grades and moisture-resistant systems — confirm from assessment

Strengths

  • Rapid application over large frame areas
  • Can follow complex or irregular section profiles
  • No fixed formwork or casing required
  • Cost-effective on large structural programmes

Limitations

  • Rough finish — not suitable for exposed steel in finished interiors
  • Containment and dust management essential during application
  • Sensitive to impact and moisture after application
  • Concealed areas must be thickness-measured before enclosure
Request Spray-System Assessment

Concrete, Masonry and Encasement

Cast, masonry or proprietary protective construction

Appearance

Structural form — significant section increase; not a coating or applied finish

Fire-Resistance Periods

Available fire-resistance periods depend on the specific tested or assessed construction, member configuration and structural design.

Thickness Control

Encasement dimensions from structural design; site-built encasement is not automatically a tested fire-resistance system

Inspection Method

Visual and structural — no DFT measurement; condition monitoring for moisture, cracking, spalling

Added Weight

Significant added weight — structural implications must be confirmed

Access Requirement

Formwork, masonry construction or proprietary assembly required; connection and penetration detailing essential

Programme Impact

Concrete curing periods; formwork removal and follow-on trades must be planned

Repairability

Crack or spalling repairs possible; structural repair involves more significant intervention

Environments

Internal and external — structural design and exposure governs

Strengths

  • Highly durable and impact-resistant
  • Integrated into building fabric — long operational life
  • Established performance basis for concrete encasement
  • Suitable for aggressive environments where coatings or boards are impractical

Limitations

  • Significant added section bulk, weight and loading on the structure
  • Programme, formwork and masonry construction requirements
  • Cannot practically expose steel for inspection without demolition
  • Connections, penetrations and services must be accommodated in the design
Request Encasement Assessment
Assessment Routes

Submit Your Project for System Assessment

No named system is presented without confirmed assessment evidence. Submit project details for system availability, documentation and specification support.

Intumescent Coating Assessment

Reactive intumescent systems for structural steel require confirmed fire-resistance evidence — assessment documentation under BS EN 13381-8 or equivalent ETA — covering the member types, section-factor range, critical-temperature range and resistance periods required for the specific project. The complete specification sequence — DFT calculation from the loading schedule, member schedule, primer, topcoat, inspection, QA and maintenance — is covered on the dedicated Intumescent Coatings page. Submit project details here for system confirmation and assessment support.

Request Intumescent Assessment

Board or Encasement Assessment

Fire-protection boards — calcium silicate, mineral fibre, gypsum-based or proprietary — and concrete or masonry encasement provide structural fire resistance within their tested or assessed build-up. The board type, thickness, number of layers, fixing system, joint treatment, framing, connection details and openings must all be confirmed from the system assessment. Site-built concrete or masonry encasement is not automatically a tested fire-resistance system — the specific construction must be confirmed as a tested or assessed configuration. Submit project details for assessment of the board or encasement route and available documentation.

Request Board or Encasement Assessment

Spray-Applied Fire Protection Assessment

Tested spray-applied passive-fire protection — which may be cementitious, fibrous or based on another documented composition depending on the system — is applied at a thickness confirmed from the product assessment for the specific section factor, member type and resistance period. The material composition and description must be confirmed from the product assessment documentation — not assumed to be cementitious. Spray systems require substrate preparation, containment and dust management during application, and thickness measurement before areas are concealed. Submit project details for assessment of the spray route and supporting evidence.

Request Spray-System Assessment

Existing-System Inspection

Visual appearance alone cannot establish the remaining fire performance of an existing system. An existing-system assessment must establish: product identity; original assessment documentation; original member schedule; applied thickness versus the required build-up; primer; topcoat; board type and fixings or spray type where relevant; adhesion or attachment; corrosion; water damage; impact damage; missing protection; altered steelwork; added services; any unauthorised overcoating; changed occupancy; and whether the current fire strategy remains consistent with the original design. Where existing protection cannot be identified or justified, removal and replacement is the appropriate route.

Request Existing-System Inspection

Structural fire design inputs confirmed?

Submit member schedule, resistance periods, section factors and fire strategy reference for system confirmation and specification support.

Specification Logic

Structural Steel Fire Protection — System Selection Decision Paths

The appropriate protection route follows from the structural fire design and the practical constraints of the project. These paths illustrate how key inputs resolve to system selection — and where assessment or redesign must precede specification.

New-build or refurbishment with confirmed fire strategy, resistance periods, section factors and critical temperatures — steel accessible for coating and DFT inspection — appearance requirement for a relatively slim paint-like finishThe structural fire design confirms the required resistance period, section factors and critical temperatures for each element. Programme and aesthetic requirements favour a thin-film reactive coating over a board or spray system.An intumescent coating system with fire-resistance evidence under BS EN 13381-8 or equivalent ETA — covering the member types, section-factor range and required resistance periods. Member-specific DFT confirmed from the approved product loading schedule. Primer and topcoat confirmed from system documentation. Full DFT records traceable to the member schedule.Intumescent Coating Assessment

Why This System Fits

The intumescent route requires confirmed fire-resistance evidence covering the specific members, section factors and resistance periods. No named product is presented without reviewed assessment. Submit project details for system and documentation confirmation. The complete specification sequence — loading schedule, DFT, primer, topcoat, inspection — is covered on the Intumescent Coatings page.

What Still Needs Verifying

Confirm assessment coverage for the actual member types and section-factor range. Confirm critical temperature matches the structural design. Confirm primer compatibility. Confirm topcoat and environmental sealer requirements. Confirm existing substrate condition on refurbishment. Confirm DFT measurement and inspection plan. Confirm QA documentation and handover evidence requirements.

Steel in a robust service environment — subject to mechanical impact, moisture, vehicle loading or high-traffic use — where board-based systems provide greater durability and installation quality assuranceIn robust environments, board systems offer greater resilience, defined installation tolerances and simpler visual inspection. Access around connections and column bases must be detailed. Programme does not require rapid re-inspection after application.A fire-protection board or encasement system assessed for the specific board type, thickness, fixing pattern, joint detail and steel section configuration. Board installation to the manufacturer's requirements. Joint and connection details confirmed. Concealed-work photographs before enclosure. Visual inspection for dislodgement, damage and moisture ingress at defined intervals.Board or Encasement Assessment

Why This System Fits

Board and encasement system availability and applicable assessment documentation must be confirmed before specification. Submit project details — member types, exposure conditions, connection details, programme — for assessment of the appropriate board route.

What Still Needs Verifying

Confirm assessment coverage for member types and section-factor range. Confirm fixing requirements, joint details and connection areas. Confirm all inaccessible areas can be detailed before enclosure. Confirm inspection access and maintenance requirements. Confirm board material is appropriate for humidity and chemical exposure.

Large frame area with complex or repetitive steel sections — programme favouring rapid area application — appearance not critical — containment manageableTested spray-applied systems can be applied rapidly over large steel areas and follow irregular profiles. Appearance is not suitable for exposed architectural steel. Containment and dust management are essential. Thickness in areas that will be concealed must be measured before enclosure.A tested spray-applied passive-fire protection system applied within its confirmed construction — confirmed thickness for the specific section factor, member type and resistance period. The material composition confirmed from the product assessment — not assumed. Thickness measured and recorded before areas are enclosed. Full thickness records and batch documentation.Spray-System Assessment

Why This System Fits

Spray system availability and applicable assessment documentation must be confirmed before specification. Submit project details for assessment of the appropriate spray route and supporting evidence.

What Still Needs Verifying

Confirm assessment coverage for the actual members and section-factor range. Confirm containment and dust-management requirements. Confirm all concealed members will be measured before enclosure. Confirm impact and moisture exposure is within the system scope. Confirm repair materials for any construction-programme damage.

Existing building — refurbishment, change of use, extension or building safety assessment — existing steel fire protection present but not fully identified or documentedThe existing protection may not be justified against the current fire strategy, occupancy or building regulations. Visual appearance alone cannot establish the remaining fire performance of an existing system. Original documents may be unavailable. The system may have been overcoated, patched, damaged or subjected to water ingress.An existing-system assessment establishing: product identity; original assessment documents; original member schedule; applied thickness versus required build-up; primer; topcoat; board type and fixings or spray type; adhesion; moisture and impact damage; corrosion beneath; any unauthorised overcoating; changed occupancy and fire strategy. The outcome determines whether repair, overcoating with a confirmed compatible system, or complete removal and replacement is appropriate.Existing-System Inspection

Why This System Fits

Contact Forti Nova to confirm the appropriate assessment route for existing protection. Where original documents are unavailable, the structural fire design may need to be re-established before any repair or replacement specification is committed.

What Still Needs Verifying

Confirm whether original specification documents are available. Confirm whether the current occupancy or fire strategy differs from the original design. Confirm whether alterations to the steelwork have affected the protected section. Confirm whether sampling and testing of existing protection is required to establish product identity.

Existing Buildings and Refurbishment

What Existing-System Assessment Must Establish

Visual appearance alone cannot establish the remaining fire performance of an existing system.

Structural steel in existing buildings may have been protected under earlier specifications using products that are no longer available, have changed formulation, or cannot be identified. Before any refurbishment, change-of-use or extension work, the existing protection must be assessed — not assumed to remain valid.

Where existing protection cannot be identified or justified against the current fire strategy and occupancy, complete removal and replacement is the appropriate route. Patching unidentified systems with new materials of uncertain compatibility must not be presented as an equivalent specification.

Where original documents are unavailable, the structural fire design may need to be re-established for the current occupancy before any specification proceeds. This must be done by the competent project design team and fire engineer.

1

Original product or system identity — from original specification documents, contractor records or sampling; not visual appearance

2

Original assessment or classification documents — confirming the system's fire-resistance evidence

3

Original member schedule — confirming the required protection build-up for each member

4

Original applied thickness or build-up — measured against the required DFT or board specification

5

Primer — identity and compatibility with any repair or overcoat material

6

Topcoat — identity and compatibility

7

Board type and fixings, or spray type — identified and confirmed from original documents or sampling

8

Adhesion or attachment — pull-off or tap test where doubt exists

9

Corrosion — at edges, connections, penetrations, fixing points and concealed interfaces

10

Water damage — ingress, freeze-thaw cycling, staining, swelling or delamination

11

Impact damage — cracking, detachment, abrasion or physical loss

12

Missing protection — at connections, penetrations, column bases or areas of known damage

13

Altered steelwork — added connections, penetrations, notches or section changes since original application

14

Added services — penetrations through protected sections or removal of protection around new service routes

15

Unauthorised overcoating — incompatible materials applied over existing protection without assessment

16

Changed occupancy — use changes that may require a higher or different resistance period

17

Changed fire strategy — updated compartmentation, revised evacuation routes or building safety assessment

18

Local repair versus removal and replacement — confirmed by competent assessment, not visual judgement

Inspection and QA

System-Specific QA Requirements

Coatings and Sprayed Systems

  • Surface preparation records — standard, cleanliness, anchor profile
  • Primer records — product, batch, DFT, environmental conditions
  • Environmental readings — temperature, relative humidity, dew-point before and during application
  • Wet-film checks during application where applicable
  • DFT or applied-thickness readings per member — recorded against member schedule
  • Gauge calibration records
  • Reading locations per member confirmed in inspection plan
  • Repairs — non-conformances, remediation and re-inspection records
  • Topcoat records — product, batch, DFT, environmental conditions

Board or Casing Systems

  • Product identification — board type, grade, batch
  • Board thickness — confirmed per member against the assessment
  • Number of layers — confirmed in all zones
  • Fixings — type, size and specification
  • Fixing centres — confirmed against installation requirements
  • Framing — position and fixity where specified
  • Joints — continuous and properly finished
  • Junctions — at connections, column bases and beam intersections
  • Penetrations — openings for services and access confirmed detailed
  • Concealed-work photographs — traceable to individual members before enclosure

All Systems

  • Approved specification — referenced to confirmed system assessment
  • Fire strategy — resistance periods for each element confirmed
  • Member schedule — DFT or build-up per member
  • Batch records — product, batch, delivery and expiry
  • Non-conformances — recorded, remediated and reinspected
  • Repairs — documented and traceable to member
  • Final inspection certification — traceable to member schedule
  • Handover documentation — system evidence, maintenance requirements
  • Maintenance requirements — inspection intervals and obligations
  • Change control — any design changes recorded before application

Records must be available for building control and the building safety case. Records document what was done — they do not guarantee acceptance by the fire engineer, building control or a future building safety assessor.

Specification Questions

Technical
Questions

Our technical team advises on system selection, design-input requirements, existing-system assessment and specification support for structural steel fire protection.

Technical Enquiry

Why does structural steel need fire protection?

Steel is non-combustible but thermally conductive. Its mechanical strength reduces significantly as temperature increases. Without passive fire protection, an unprotected structural steel member can lose sufficient load-bearing capacity to cause collapse within minutes of fire exposure. Building Regulations Approved Document B, BS 9999 and BS 9991 require structural elements to maintain their load-bearing function for a defined resistance period to allow safe evacuation and fire-service intervention. Passive fire protection slows the rate at which the steel heats, extending the time before its critical temperature is reached.

What is structural fire resistance?

Structural fire resistance is the ability of a construction element to maintain its load-bearing capacity (R), insulation (I) and integrity (E) during a standard fire exposure for a stated period. For structural steel, the load-bearing requirement (R) is the primary criterion — the member must not fail structurally for the required duration. The resistance period is not an inherent property of a material or product; it depends on the specific tested or assessed system, the member configuration, the section factor and the critical steel temperature. Each structural element must be assessed individually against the project's structural fire design.

What is the difference between reaction to fire and structural fire resistance?

These are different characteristics measured by different test standards serving different functions. Reaction to fire (EN 13501-1) describes how a product contributes to fire growth, smoke production and flaming droplets if it becomes involved in a fire. A2-s1,d0 is a reaction-to-fire classification for surface linings. It does not provide structural fire resistance. Structural fire resistance (EN 13501-2, BS EN 13381) describes how a construction element maintains its load-bearing capacity, insulation and integrity during a standard fire exposure for a stated period. A product with an A2-s1,d0 surface classification is the correct specification for a wall, ceiling or soffit classification requirement — not for a beam or column requiring structural fire resistance.

What fire-resistance periods can structural-steel protection systems provide?

Available fire-resistance periods depend on the specific tested or assessed system, member configuration, design inputs and installed build-up. Periods of 30, 60, 90 and 120 minutes are achievable in principle for intumescent, board, spray and encasement routes — but the achievable period for a specific member on a specific project must be confirmed from the product or system assessment documentation for the actual section factor, critical steel temperature and member type. No route inherently provides any period without confirmed assessment coverage for the exact member configuration.

How is the correct passive-fire system selected?

Route selection follows from the structural fire design inputs, the practical constraints of the project, and the available assessment evidence for each system. Intumescent coatings are suited to exposed architectural steel where a slim profile and paint-like appearance are required. Board systems are suited to robust environments where impact resistance, moisture tolerance and defined installation tolerances are important. Tested spray-applied systems are suited to large frame areas where speed and area coverage outweigh appearance requirements. Encasement — concrete, masonry or proprietary casing — suits very aggressive environments where long-term durability takes precedence. No single route is universally appropriate, and each must be confirmed against the structural fire design inputs before specification.

What is the difference between intumescent coating and fire-protection boards?

Intumescent coatings are reactive thin-film or thick-film systems that expand under heat to form an insulating char. They provide a slim, paint-like finish and are suited to exposed architectural steel. The required dry-film thickness is calculated per member from the approved product loading schedule using section factor and critical temperature — this varies across every member on the project. Board systems are fixed casings made from calcium silicate, mineral fibre, gypsum-based or proprietary board products. They are applied in defined layers and fixings around the steel member and are suited to robust environments where impact resistance and moisture tolerance are required. Board installation is visually inspectable; intumescent DFT requires measurement. The complete intumescent specification sequence is covered on the Intumescent Coatings page.

What is the difference between intumescent coating and spray-applied fire protection?

Intumescent coatings are reactive materials that expand under heat. They produce a slim, paint-like result suitable for exposed steel and are applied to member-specific thickness requirements confirmed from a loading schedule. Tested spray-applied passive-fire protection — which may be cementitious, fibrous or based on another documented composition depending on the system — is applied at a uniform thickness confirmed from the product assessment for the section factor and resistance period. Spray systems are rapid on large frame areas and can follow complex profiles, but are not suitable for exposed architectural finishes and require thickness measurement before concealment. Neither system should be described as cementitious unless that specific composition has been confirmed for the selected product.

What is a section factor?

Section factor (Hp/A in m⁻¹) relates the heated perimeter of a steel section to its cross-sectional area. More slender sections — with a higher section factor — heat more rapidly under fire conditions and require greater protection to achieve the same resistance period. The section factor changes with member type (beam or column), section profile (universal section, hollow section, cellular or castellated), exposure (three or four sides heated), and connection conditions. It must be calculated for each actual member and exposure condition — not estimated from general tables or assumed from a section catalogue reference. Forti Nova must not calculate or guess the structural fire-design inputs; they must be supplied or confirmed by the competent project design team.

What is critical steel temperature?

Critical steel temperature is the temperature at which a member's load-bearing capacity reduces to the level corresponding to the design load under fire conditions. It is established by the structural fire design (EN 1993-1-2) and depends on the structural utilisation or load ratio of each member. It is not universally fixed at 550°C — this is a commonly cited default, not a universal physical property. A more heavily utilised member has a lower critical temperature and may require greater protection than a lightly loaded member of the same section. The critical temperature for each member must come from the structural fire design and must be used in the approved product loading schedule to determine required protection thickness.

Do beams, columns, braces and connections require different protection?

Yes. Beams, columns, braces, connections and built-up members each have different section geometries, section factors and exposure conditions. Universal beams typically have higher section factors than universal columns of equivalent weight — and therefore may require greater protection for the same resistance period. Connections, column bases and member junctions require specific detailing to maintain the protection at the interface. Hollow sections (CHS, RHS) heat differently from open sections (UB, UC) and require confirmation that the chosen protection system's assessment covers the specific section type. Each member type must be assessed individually.

Can hollow steel sections be protected?

Yes. Hollow sections — circular hollow sections (CHS) and rectangular hollow sections (RHS) — can be protected by intumescent coatings, boards and spray-applied systems. However, not all intumescent systems are assessed for all hollow section types, and the section factor for a hollow section is calculated differently from an open section. The protection system assessment must confirm coverage of the specific hollow section profile, dimensions, section factor range, and exposure category. Where a hollow section is filled with water or concrete as a protection strategy, the design must be confirmed by the structural fire engineer as a specific tested or assessed construction.

How are cellular or castellated beams assessed?

Cellular and castellated beams — fabricated from universal beam sections with openings cut into the web — have complex geometries that differ from the parent solid section. The section factor, critical temperature, web-post behaviour and opening configuration each affect the fire-resistance requirement and the protection build-up. Not all standard assessment documents cover cellular or castellated sections directly. Specialist fire engineering analysis may be required. Protection applied to the solid portions of the section must be confirmed as covering the web-post zones and opening edges adequately. Assessment coverage for the specific beam configuration and opening arrangement must be confirmed before specification.

Can fire protection be applied over corroded steel?

No — not without first addressing the corrosion. Surface corrosion must be removed to achieve the required surface cleanliness and anchor profile before any primer or protection system is applied. Where corrosion has caused section loss, the structural engineer must assess the remaining structural capacity — no protection coating restores lost steel section or structural capacity. Applying protection over corroded steel conceals active deterioration without arresting it, and may cause premature adhesion failure or delamination under fire conditions.

How is existing structural fire protection identified?

Existing protection should be identified from the original specification documents, contractor records, Building Control file, or the building owner's golden thread records. Visual appearance alone cannot establish the product identity, applied thickness, or remaining fire performance of an existing system. Where original documents are unavailable, sampling and laboratory analysis of the existing material may be required to establish composition. An existing system that cannot be identified cannot be specified as 'remaining compliant' — the fire strategy must be re-established against the current occupancy and building regulations before any repair or continuation is confirmed.

Can existing protection be locally repaired?

Local damage can be repaired if the existing system has been identified, the original loading schedule and required protection thickness are known for the affected members, and a compatible repair material is confirmed from the system documentation. Repair materials must be compatible with the existing system — applying a different product over an identified existing protection introduces an untested interface. Where the existing protection cannot be identified, widespread damage, water ingress, detachment, cracking or corrosion beneath is found, or the required DFT cannot be verified, complete removal and replacement is the appropriate route.

How are coating or spray thicknesses inspected?

For intumescent coatings: dry-film thickness (DFT) is measured using calibrated electronic film-thickness gauges on the cured film, at a number and distribution of positions per member confirmed in the inspection plan. Readings must be recorded against individual member references in the member schedule. Wet-film checks during application assist process control but do not substitute for DFT measurement. For tested spray-applied systems: applied thickness is measured using pins or gauges before areas are concealed or enclosed. Once the surface is enclosed, measurement is no longer possible. All readings and member references must be documented and retained for the building safety case.

How are board systems inspected?

Board systems are inspected visually at installation and at defined maintenance intervals. Installation inspection should confirm: product identity and batch; board thickness and number of layers; fixing type, size and centres; framing arrangements where required; joint and junction details at connections, corners and penetrations; and that no unprotected gaps or access openings have been left undetailed. Concealed-work photographs must be taken before enclosure. Photographs must be traceable to individual members. During the building's operational life, inspection should confirm: boards are intact and not dislodged; no moisture damage, staining or deformation; no penetrations or modifications have compromised the protection.

Can structural fire-protection work be undertaken in occupied buildings?

In some cases, subject to the method statement, zone management, containment, dust and VOC controls, occupancy controls and the applicable safety assessment. Work involving preparation — abrasive blasting, grinding, shot blasting — requires strict containment and is generally not compatible with occupied areas. Application of solvent-based intumescent systems in occupied zones requires ventilation and occupancy exclusion during application and cure periods. Water-based systems may offer lower solvent emissions. Spray-applied systems require dust containment. The method statement and risk assessment must address re-occupation conditions. Programme and access must be agreed with the building manager before work begins in any occupied or partially occupied building.

Who determines the system and the required performance?

The fire engineer or structural engineer determines the required fire-resistance period, structural fire design inputs — section factors, critical temperatures, load ratios — and the fire strategy for each element. The protection system and required thickness for each member are then specified against those inputs using the product or system assessment documentation. Building Control or an approved inspector confirms compliance with Building Regulations under the project's approval route. Forti Nova must not calculate or guess the structural fire-design inputs; they must be supplied or confirmed by the competent project design team. Forti Nova provides specification support and system documentation — not structural fire engineering.

When is removal, replacement or another construction solution more appropriate?

Removal and replacement rather than repair is appropriate where: the existing protection cannot be identified or its original assessment documentation cannot be located; widespread damage, moisture ingress, corrosion beneath, or adhesion failure is found on inspection; the original DFT cannot be verified for the majority of members; the system has been incompatibly overcoated; or the fire strategy or occupancy has changed and the existing protection was not designed for the current requirement. Another construction solution — such as structural redesign, the use of fire-resistant steel, or alternative building layout to reduce the required fire-resistance period — may be appropriate where the protection route is unworkable due to programme, access, environment or cost constraints. These decisions must be made by the competent project design team and fire engineer, not by the protection contractor alone.

When Specification Cannot Proceed

Structural Steel Fire Protection — Suitability Exclusions

1

Fire strategy is absent or unresolved — the required fire-resistance period for each structural element cannot be established without a confirmed fire strategy.

2

Required structural fire-design inputs are unavailable — fire-resistance period, critical steel temperature, structural utilisation or load ratio, section factor, member type, geometry and exposure cannot be assumed or guessed by the protection contractor.

3

The required fire-resistance period is unsupported by available assessment evidence for the specified system, member type and section-factor range.

4

The member or configuration lies outside the assessed scope of the selected system — cellular beams, hollow sections, connections or built-up members must be confirmed within the evidence.

5

Steel is structurally unsound — corrosion, section loss or structural damage must be assessed and remediated by a structural engineer before any protection is applied. Protection does not restore lost steel section or structural capacity.

6

Existing protection cannot be identified or justified against the current fire strategy, occupancy and structural fire design — visual appearance alone cannot confirm remaining fire performance.

7

Required substrate preparation cannot be achieved — contamination, corrosion, existing incompatible coatings or access restrictions prevent preparation to the standard required by the system assessment.

8

Environment lies outside the system assessment limits — internal-grade systems applied externally, moisture-sensitive systems in humid zones, or chemically aggressive conditions not covered by the assessment.

9

Required thickness or build-up cannot be installed in the available space — section-size constraints, existing services or architectural limits prevent the confirmed protection build-up.

10

Access prevents application or inspection to the required specification — DFT measurement, board fixing, spray containment, thickness checks in concealed areas, or post-application inspection cannot be completed.

11

Interfaces, connections or penetrations cannot be properly detailed — unprotected junctions, service penetrations or connection zones will compromise the overall fire performance regardless of protection applied to the main sections.

12

Programme does not allow adequate preparation, installation, cure or inspection before the building is loaded, occupied or handed over.

13

Required QA and handover documentation cannot be produced — member schedule, DFT or thickness records traceable to individual members, batch information, inspection certification and maintenance requirements must be available for the building safety case.

14

The requirement is reaction-to-fire surface classification (e.g. A2-s1,d0) rather than structural fire resistance — see Fire Protection Coatings for the surface-coating specification route.

15

The requirement is fire stopping, penetration sealing, cavity barriers or compartmentation interfaces — these are distinct passive-fire products not covered on this page.

16

Another tested construction or passive-fire route is more appropriate for the specific member type, environment, programme or durability requirement — no route is universally preferable, and the decision must be made with the competent project design team and fire engineer.

Knowledge Hub

Structural Steel Fire Protection — Connected Knowledge

Structural steel fire protection connects to the structural fire design, the fire strategy, substrate preparation, existing-building assessment, and the broader passive-fire and surface-coating framework.

Ready to Proceed?

Begin Structural Fire Protection Assessment